NWPC is in the final stage of assembling its second shipment of mining equipment, which was delivered to Nakhodka seaport from Japan by sea and to Titan railroad station by railroad. All the equipment is being assembled on-site at the MPC. This new shipment of mining equipment, consisting of an excavator, bulldozer and 490-ton dump trucks, will accelerate the pace of construction considerably. The excavator with a bucket capacity of 11 m3 was assembled first and is already working on the opencast mine construction. A third shipment of equipment has been ordered and will be delivered soon.