From the Mediterranean to the Arctic

15.04.2011

The first equipment for the concentration plant under construction has arrived at the Oleniy Ruchey MPC site. Diemme filter presses were delivered by railroad from Italy in 16 carriages. It took three days to unload all the equipment at the Titan railroad station. After customs clearance, the filter presses will be moved to the MPC site and installed at the filtration and drying block of the concentration plant, built by Trest-2.

While this was the first delivery of equipment for the concentration plant, the opencast mine has already received its third shipment, an excavator and 4 dump trucks from Komatsu (Japan). Mining operating at the pit are requiring an increasing volume of equipment.